Work Days

Updated:       June 13, 2018    10:05 AM

From Work Day 2018 June 12:  Recent heavy rains washed a lot of debris down the hill.  Logs and boulders completely blocked the passage way under the bridge and diverted the water toward the tunnel’s entrance.  Mud, sand, & gravel covered the tracks about 6 inches deep in front of the gate.  It was raining so everyone got drenched during the couple hours it took to clear the tracks and dig out the passage way.  Thanks to Eric S, Howard W, Jim H, John L, and Larry W for clearing the tracks and working on other tasks. 

  

Above left is before.                                              Above right is after.

It is still a little dirty and needs additional clearing of the debris.  

———————–

Thanks to all who showed up on Saturday, June 9 for checking equipment, replacing the one engineer’s seat, and other work performed during the day.  

——————————–

The switch below left was damaged by a derail during the Heritage Day run but was fixed on the May 29 work day.  Thanks to Howard, Bob, Larry, and John for their efforts on Tuesday.   

  

——————–

Thanks to Bob, Larry, and John L for working Saturday, May 26th.  Thanks to Don and Lois for bringing bottled water.

On the Saturday, May 26th workday, Bob noticed that the track had been damaged by the construction equipment.  Note the big dip just this side of the bridge. 

 Bob used the rail straightener on each rail to remove the dip.

——————————————–


 Thanks to all of the members that worked on MAY 08 and 15, 2018.  

AugerFromHill_20180508_111239 JimGrinding_20180508_103804 WillChainSawing_20180508_121011

 

——————-

Thanks to Eric S, Bob S, and John L for working a long day on Tuesday, Apr 9th.  They checked out both lawn mowers and both work fine.  Eric mowed around all of the track while Bob used the leaf blower to clear out leaves from the switch boxes and off of the track.  John L cut back a lot of the honeysuckle around the West part of the track.  

——————————————-

Larry_1932_20180402_151627_Comp Larry with Loco 1932.

————————————————

Update: The pictures below were taken on March 03, 2018 but nothing has changed since then til now.  They show steel plates over all three tracks for heavy equipment to access the inner loop area for the new tower construction.

PlatesOverTracks_20180303_145853_Crop WestGate_20180303_145930

——————————

Pictures from Work Day on Feb 27, 2018:  Also working this day, but not pictured,  were: Ken H, Larry W, and John L.    Below left is Brad in front with Norm and Howard to the left in back.  They are carrying the last load of holiday decorations away for storage.  The group in the upper right of this picture is Brady and 2 others.  The picture below to the right is Howard and Don H removing decorations at the loading station.

BradNormHoward_Finished_20180227_121849 HowardAndDonH_20180227_100745

Below left are Norm and Brad taking decorations down at the far west end.  Below right are the steps by the switch tower – they need some straightening.

NormAndBrad_20180227_103802 StepsBySwitchTower_20180227_122755

————————————

CPR&SS Members:  The pictures immediately below were taken on Tuesday, Nov 21, 2017 as preparations continued for the Carillon Christmas which ran from Nov 29th  through Dec 30th.   The next train run is April 07, 2018.

—————————————-

Below is Howard W. by the little tower, Bob S re-leveling the stub switch, Jim H.  and Howard putting the final touches on the tunnel, and Norm G. hanging the power for a display to be put up.  Not shown are Don H. and Larry W. who also helped and had their own projects.

20171121_123948 20171121_124520 20171121_133852 20171121_134457

—————————————————————————–

The next three pictures were taken on the work day on Tuesday, Oct 10.  Right below is Jim H  with a possible approach to a train tunnel for the holiday train storage.  It covers two tracks this year.  Tarps will be supported by the PVC pipes and fittings.  Other approaches are still being considered.  Other workers present this day were Bob S, Howard W, and Jim E who worked on the new track extension and John L  who installed the switch light shown below.

20171010_111959

Below is Larry W  replacing the dirt and gravel over the conduit supplying power to the switch signal lights that are being installed.

??????????????

Larry moving dirt.

??????????????

Above is the first switch light being tested on power from the Yoder Engine House.

———————————————————————

The pictures below were taken at the Work Day on Sept 26, 2017.  Larry W.  and John L.  were workers also this day.

 

??????????????

Jim H.   removing loose screws

??????????????

Howard W.     after cutting the grass

 

——————————————————-

At the March 02, 2017 club meeting, it was decided to have work days on Tuesdays and non-run Saturdays (if the weather permits).   Most workers show up between 9 and 10 AM.  If you come, we will put you to work on the track, grounds, equipment, etc – what ever needs attention.  Thanks, in advance, for your support!